Draft Environmental Impact Statement. Space Shuttle Advanced Solid Rocket Motor Program


Book Description

The proposed action is design, development, testing, and evaluation of Advanced Solid Rocket Motors (ASRM) to replace the motors currently used to launch the Space Shuttle. The proposed action includes design, construction, and operation of new government-owned, contractor-operated facilities for manufacturing and testing the ASRMs. The proposed action also includes transport of propellant-filled rocket motor segments from the manufacturing facility to the testing and launch sites and the return of used and/or refurbished segments to the manufacturing site.




Environmental Impact Statement Space Shuttle Advanced Solid Rocket Motor Program


Book Description

The proposed action is design, development, testing, and evaluation of Advanced Solid Rocket Motors (ASRM) to replace the motors currently used to launch the Space Shuttle. The proposed action includes design, construction, and operation of new government-owned, contractor-operated facilities for manufacturing and testing the ASRMs. The proposed action also includes transport of propellant-filled rocket motor segments from the manufacturing facility to the testing and launch sites and the return of used and/or refurbished segments to the manufacturing site. Sites being considered for the new facilities include John C. Stennis Space Center, Hancock County, Mississippi; the Yellow Creek site in Tishomingo County, Mississippi, which is currently in the custody and control of the Tennessee Valley Authority; and John F. Kennedy Space Center, Brevard County, Florida. TVA proposes to transfer its site to the custody and control of NASA if it is the selected site. All facilities need not be located at the same site. Existing facilities which may provide support for the program include Michoud Assembly Facility, New Orleans Parish, Louisiana; and Slidell Computer Center, St. Tammany Parish, Louisiana. NASA's preferred production location is the Yellow Creek site, and the preferred test location is the Stennis Space Center.







Shuttle Rocket Motor Program: NASA Should Delay Awarding Some Construction Contracts


Book Description

In January 1992, the President proposed termination of the National Aeronautics and Space Administration's (NASA) Advanced Solid Rocket Motor (ASRM) program. However, he left open the possibility that the program could be reinstated during congressional budget deliberations for fiscal year 1993. According to NASA, if the program is continued, maintaining the current program schedule is critical so that the advanced motors will be available to transport the Space Station Freedom's laboratory module in February 1997. As a result, NASA is pursuing the facility construction program for fiscal year 1992 as originally planned. The purpose of this letter is to identify construction activities that could be delayed pending a decision on the future of this program and still not adversely affect the scheduled ASRM launch date.










Analysis and Effects of the Advanced Solid Rocket Motor on the Space Shuttle Elements


Book Description

This interim final report summarizes the activities and major accomplishments under NASA/MSFC Contract NAS8-39235 for the initial two year contractual effort beginning October 1, 1991, and ending September 30, 1993. It is not intended as an exhaustive treatment or review of any particular technical issue which was addressed during this two-year period, but does provide an overview of the many induced environment studies and test support activities undertaken by REMTECH and its subcontractors during this two-year period. The initial scope of work has been pursued vigorously through this two-year period by separating the effort into five functional areas. The five functional areas are ascent plume radiation, ascent plume convection, ascent aerodynamic heating, launch stand environments, and reentry heating. A work breakdown structure (WBS) for each functional area was devised to permit nearly autonomous activities within each functional responsibility while maintaining commonality in reporting procedures and cost accounting. The contract was modified 11 times to provide incremental funding and to expand the scope of work. Additional work breakdown structure was incorporated to meet the expanded scope. A contract chronology is provided in Section 2. The initial scope of work, expanded scope, and corresponding WBS designation are described in Section 3. A summary review of major accomplishments is also provided in Section 4 to show the breadth of activities and extent of reporting. Reports, meetings, test activities, and other accomplishments within each functional area are also summarized by WBS heading in the appendices. Unspecified Center...




Tests of the Redesigned Solid Rocket Motor Program


Book Description




Data Communication Network at the Asrm Facility


Book Description

This report describes the simulation of the overall communication network structure for the Advanced Solid Rocket Motor (ASRM) facility being built at Yellow Creek near Iuka, Mississippi as of today. The report is compiled using information received from NASA/MSFC, LMSC, AAD, and RUST Inc. As per the information gathered, the overall network structure will have one logical FDDI ring acting as a backbone for the whole complex. The buildings will be grouped into two categories viz. manufacturing intensive and manufacturing non-intensive. The manufacturing intensive buildings will be connected via FDDI to the Operational Information System (OIS) in the main computing center in B_1000. The manufacturing non-intensive buildings will be connected by 10BASE-FL to the OIS through the Business Information System (BIS) hub in the main computing center. All the devices inside B_1000 will communicate with the BIS. The workcells will be connected to the Area Supervisory Computers (ASCs) through the nearest manufacturing intensive hub and one of the OIS hubs. Comdisco's Block Oriented Network Simulator (BONeS) has been used to simulate the performance of the network. BONeS models a network topology, traffic, data structures, and protocol functions using a graphical interface. The main aim of the simulations was to evaluate the loading of the OIS, the BIS, and the ASCs, and the network links by the traffic generated by the workstations and workcells throughout the site. Moorhead, Robert J., II and Smith, Wayne D. Unspecified Center...