Evaluation of Bridge Approach Slabs, Performance and Design


Book Description

The design changes in the 1990s to bridge approaches resulted in approach slabs of about 8m in length supported at one end on the bridge abutment and at the other by a sleeper beam resting on the embankment. These slabs have not performed adequately due primarily to excessive deformation of the foundation and fill soils under the slab and sleeper beam. Survey questionnaires were administered for resident engineers in MoDOT and neighboring states to assess overall performance. Two bridge sites were selected for more detailed study of the deformation mechanisms. Analyses involving modeling using a finite element method program were conducted using soil properties obtained from drilling, sampling and laboratory testing at the study sites. Conclusions and recommendations are in the following categories: initiating programmatic instrumentation and monitoring plans for approach embankments; enhanced drilling, sampling and analysis at locations of future embankments; geosynthetic reinforcement of the embankment; staged construction; separating grading and paving contract; abutment and drainage details; and improved compaction specifications.




Bridge Approach Slabs for Missouri DOT


Book Description

Based on a recent study on cost efficient alternative bridge approach slab (BAS) designs (Thiagarajan et al. 2010) has recommended three new BAS designs for possible implementation by MoDOT namely a) 20 feet cast-inplace slab with sleeper slab (CIP20SLP) - for new construction on major roads, b) 25 and 20 feet precast-prestressed slab with sleeper slab (PCPS20SLP)- for replacement and new construction applications on major and minor roads, and c) 25 feet modified BAS without a sleeper slab for new CIP construction on minor roads (CIP25NOSLP). The objective of the project here is to evaluate and compare the field performance of recommended BAS designs, their constructability, and their impact on cost and schedule to the current MoDOT BAS design. Two PCPS20SLP, one CIP20SLP and two CIP25NOSLP implementations have been implemented and studied for this report. One PCPS20SLP panel was also tested in the laboratory for several washout conditions and for its ultimate capacity. Based on field observations, data recorded and analyzed, preconstruction and post construction cost analyses this study has found that all the suggested designs are performing well and are lower in cost compared to current designs used in practice.










Instrumentation and Monitoring of Integral Bridge Abutment-to-approach Slab Connection


Book Description

The Iowa Department of Transportation has long recognized that approach slab pavements of integral abutment bridges are prone to settlement and cracking, which manifests as the "bump at the end of the bridge". A commonly recommended solution is to integrally attach the approach slab to the bridge abutment. Two different approach slabs, one being precast concrete and the other being cast-in-place concrete, were integrally connected to side-by-side bridges and investigated. The primary objective of this investigation was to evaluate the approach slab performance and the impacts the approach slabs have on the bridge. To satisfy the research needs, the project scope involved a literature review, survey of Midwest Department of Transportation current practices, implementing a health monitoring system on the bridge and approach slab, interpreting the data obtained during the evaluation, and conducting periodic visual inspections. Based on the information obtained from the testing the following general conclusions were made: The integral connection between the approach slabs and the bridges appear to function well with no observed distress at this location and no relative longitudinal movement measured between the two components; Tying the approach slab to the bridge appears to impact the bridge; The two different approach slabs, the longer precast slab and the shorter cast-in-place slab, appear to impact the bridge differently; The measured strains in the approach slabs indicate a force exists at the expansion joint and should be taken into consideration when designing both the approach slab and the bridge; The observed responses generally followed an annual cyclic and/or short term cyclic pattern over time.







Field Demonstration of New Bridge Approach Slab Designs and Performance


Book Description

The Louisiana Department of Transportation and Development (DOTD) has initiated a major effort to minimize the bridge end bump problem associated with differential settlement. As a result, a new design for the approach slab was proposed, which requires increasing the slab flexural rigidity (EI), and using reinforced soil foundation (RSF) to support the slab and traffic loads at the roadway pavementapproach slab joint (R/S joint). Reinforcing the soil underneath the strip footing will result in increasing the soil's bearing capacity and reducing the embankment settlement by redistributing the loads imposed by the slab and traffic over a wider area. Bayou Courtableau Bridge was selected as a demonstration project to evaluate, validate, and verify the new bridge approach slab design method proposed in a previous study. The east and west approach slabs at Bayou Courtableau Bridge are 40 ft. long by 40 ft. wide. The west approach slab was designed using the proposed new method with slab thickness of 16 in., while the east approach slab was designed using the traditional method with slab thickness of 12 in. The pavement end side of the approach slab was supported by a 4.0-ft. wide strip footing with the soil underneath it reinforced by six layers of geogrid placed at a vertical spacing of 12 in. The geosynthetic reinforced soil below the strip footing was designed according to the methodology proposed in previous study. The west approach slab was instrumented with pressure cells to measure the pressure distribution underneath the footing and contact pressure underneath the slabs. Strain gauges were used to measure strain distribution along geogrid reinforcement and sister-bar strain gauges to measure strains within the slab. The east approach slab was instrumented with pressure cells to measure the contact pressure underneath slab. Two static load tests were conducted on both the west and east approach slabs at two different times after construction. The performance of the approach slabs, including deformation and internal stresses of concrete slab, contact stresses between slab and embankment, stress distributions within reinforced soil foundation, and strain distributions along the geogrid, was monitored during the tests. The test results indicated that the west approach slab (with new design) lost most of its supports from the soil; while the east approach slab (with traditional design) kept losing its contacts from the soil starting from the bridge side towards the pavement side after about a year and half. The roughness profiles show better performance of the new approach slab system with much lower International Roughness Index (IRI) values. The year and a half monitoring program at Bayou Courtableau Bridge demonstrated much better performance of the new approach slab design system (west approach slab) compared to the traditional design. The magnitude and rate of embankment settlement at Bayou Courtableau Bridge site was also monitored (for the two embankment sides) during and after the construction, and the results were compared with the laboratory calculated settlements and the piezocone penetration test (PCPT)-based settlement prediction methods. The results showed better predictions using PCPT methods as compared to laboratory results.







Recommendations for Design, Construction, and Maintenance of Bridge Approach Slabs


Book Description

Settlement and heave related movements of bridge approach slabs relative to bridge decks create a bump in the roadway. Several problems arise from these bumps, which include poor riding conditions, potential vehicle damage, loss of vehicle control causing injuries or even casualities [i.e., casualties], lowered perception of the department's road works, increased maintenance works, and constant delays to rehabilitate the distressed lanes. All these make this bump problem a major maintenance problem in Texas. Several mitigation methods have been employed, and the results are not always satisfactory. In the present research, two treatment methods are investigated for controlling settlements of approach slabs of new bridge construction. Researchers from UTA and UTEP performed two phases to accomplish these studies. During the first phase, the documented information that covers various methods used so far for approach slab settlement mitigation technologies is compiled and presented. The second and final phase focused on field evaluation studies of deep soil mixing and light weight embankment fill treatment methods in reducing settlements. A few other technologies were also evaluated for reducing settlements of existing bridge approach slabs. Both design and construction specifications of the new methods that provided effective treatments in field conditions are presented.




Design and Construction of Bridge Approaches


Book Description

Includes case histories of the Dumbarton Bridge (San Francisco Bay, Calif.), the Rainier Avenue Embankment (Seattle, Wash.) and the Gallows Road Grade Separation (Fairfax, Va.)