Book Description
This report describes the need for a 230-kV overhead transmission line to supply power from Sidney, Nebraska to eastern Colorado. The alternative scenario compared to construction of the line is No Action. Rejected alternatives include underground lines and different routing paths, with a possible extension to the Sterling area. Both scenarios are evaluated for environmental effects, cost, and consequences for the eastern Colorado region. The proposed route is determined to be the environmentally preferred choice. 120 refs., 6 figs., 13 tabs. (MHB).