National Dam Inspection Program. Bunnell's Pond Dam (NDI ID Number PA-00170, DER ID Number 64-29), Delaware River Basin, Carley Brook, Wayne County, Pennsylvania. Phase I Inspection Report


Book Description

The purpose of the inspection is to determine if the dam constitutes a hazard to human life or property. Bunnell's Pond Dam is located on Carley Brook in Honesdale Borough, Wayne County, Pennsylvania. The overall appearance of the dam and appurtenant structures is fair.




National Dam Inspection Program. Freethy Dam (NDI ID Number PA-00171, DER ID Number 64-160), Delaware River Basin, Carley Brook, Wayne County, Pennsylvania. Phase I Inspection Report


Book Description

Based on the criteria established for these studies, Freethy Dam is judged to be unsafe, nonemergency, because the spillway capacity is seriously inadequate. The recommended Spillway Design Flood (SDF) for the size and hazard classification of the dam varies between 1/2 of the Probable Maximum Flood (PMF) and the PMF. Based on the size of the dam and reservoir, the 1/2 PMF is selected as the SDF. The existing spillway will pass only about 2 percent of the PMF before overtopping of the dam occurs. It is judged that the dam could not withstand the depth and duration of overtopping during storms of only 20 percent of the PMF. Failure of the dam would cause an increased hazard for loss of life downstream. Overall, the dam is judged to be in good condition.










National Dam Inspection Program. Kellow Lake Dam (NDI ID Number PA- 01105, DER ID Number 64-63), Delaware River Basin, Tributary to Carley Brook, Wayne County, Pennsylvania. Phase I Inspection Report


Book Description

Based on available records, visual inspection, calculations, and past performance, Kellow Lake Dam is judged to be in fair condition. The recommended Spillway Design Flood (SDF) for the size and hazard classification of the dam varies between 1/2 of the Probable Maximum Flood (PMF) and the PMF. Based on the downstream conditions, the 1/2 PMF is selected as the SDF. Under existing conditions the spillway will pass only about 22 percent of the PMF. If all stoplogs were removed from the spillway, the spillway would pass about 51 percent of the PMF. The spillway capacity is rated as adequate provided that all stoplogs are removed. Potential stability problems exist for the dam. A slope failure occurred over one reach at an unknown time in the past. Although the damage in that reach does not appear to be serious, a similar failure could occur in a more critical area and threaten the overall stability of the dam. In addition, steel beams that support the roof of the spillway outlet channel are badly corroded and create a hazardous condition. Although some maintenance has been performed, the program should be expanded to correct all deficiencies.